CONSTRUCTION MANAGER/ GENERAL CONTRACTOR
The Downtown Development Authority (DDA) is seeking proposals from qualified Contractors for Construction Manager/General Contractor (CM/GC) services related to the construction of the multi-phased Alley Renovation Program for the following alleys:
Phase 1 (Design 2020- Construct 2021):
- West Oak Street to West Olive Street (one block west of South College Avenue)
- Tenney Court Alley extension, North Mason Street to LaPorte Avenue (behind Civic Center Parking Structures)
Phase 2 (Design 2022 – Construct 2023):
- Harper Goff Alley (Pine Street to Jefferson Street (behind The Exchange)
- East Laurel Street to E. Myrtle Street (one block east of South College Avenue)
- West Olive Street to West Magnolia Street (one block west of South College Avenue)
CM/GC Procurement Schedule
RFP Issued for Advertisement – October 1, 2020
Pre-Proposal Meeting – October 7, 2020
Email Deadline for written questions: October 13, 2020 at 5:00pm
Addendum released by – October 16, 2020
RFP submittals due: October 22, 2020 at 3:00pm
Interview Notifications – October 28, 2020
Interviews – Week of November 2, 2020
Selection Notification – By November 12, 2020
See the link below for complete request for proposal.
http://www.bidnetdirect.com/colorado/city-of-fort-collins
Questions concerning the scope of the project or bid submitted should be directed to Project Manager, Todd Dangerfield at (970) 419 – 8254 or tdangerfield@fcgov.com